Task/Process and Result

I was asked by a builder if I could demolish a part of the building that he was going to do a major renovation on. The block was split and the building had to be shifted.

We had to clean out everything from under the house disconnecting all the services. The deck was to be cut back to the internal walls as you will see from the photos. Asbestos had to be stripped out and the house decontaminated before we could start demolishing. Unfortunately I only have  few photos but you can see the job at hand. This job was done in a few days with three people.