Category Archives: Renovations

Task

A client bought a 60’s build house and started to strip out the kitchen, laundry and dinning area but soon discovered that it was a lot more involved then they thought. Upon their research and recommendations my services were requested.

IMG_6518

IMG_6521

So this is what I was confronted with. Their plan was to open up that internal area and incorporate it with the outdoors. Allow more natural light into the house and a sense of height and grander. It also needed to look the original part of the build so the bricks were going to be recycled.

 

 

The Challenges

The bricks were to be cleaned and we only had the original bricks as a source for our build as the colour age and look of brick is not acquirable.

IMG_6566

Asbestos sheeting was also present in the work area so caution and proper procedures were put in place.

The other challenge was the site access. Everything had to be moved by person up slope to the backyard. So moving soil and building waste to and through was going to be pretty labour intensive.

IMG_9621

A boom pump definitely had to be costed into the works.

IMG_9740

 

 

 

Task

The client purchased the house but was unhappy with the functionality of the kitchen the rear deck and living area.  It was outdated and needed a fresh approach. The colour was an apricot colour and that definitely had to go. Structural changes to opening sizes as well as repairs to flooring and a full list of other things.

IMG_8059 copy

IMG_8057 IMG_8069

Lounge external wall area also had to be removed and bifolds put in place.

IMG_8220 edited

Master bedroom cupboards needed a finish closed build to match existing.

IMG_5893

And so we began chopping and ripping things out while supporting the structures as we went along.

 

The Process Continued

Floor repairs. Borers had a field day in the old hoop pine floors. It was old damage but none the less had to be repaired.  So I started cutting out the affected areas.

IMG_8275 IMG_8276 IMG_8279 IMG_8278IMG_8280The bedrooms where the repair was done came up well after the sanding, staining and varnish. We did have trouble with old stains coming through so we had to re sand many sections to get the right finish.

IMG_8397

Inbuilt cupboard and top bulkhead built to replicate the bottom half.

IMG_8371

 

IMG_8393

Sanding and cleaning of the walls, doors and the windows was done throughout the house two levels. IMG_8174 IMG_8193

IMG_8095 IMG_8340

Task

We were recommended by a friend of the client whom was a previous client of mine. What was required was to do rectification works from a previous builder who had built the structure about ten years ago. Jobs like this are really challenging for everyone involved. First of all the clients feel ripped off and need to undo what they had paid a lot of money for.

This costs twice as much because you need to investigate and pull apart any suspected sub standard work as well as rectify works along with building new structures and incorporating it all into one package so that the final result looks and feels like a first time build only. So when you build it’s not a smooth run initially till you get all the logistics done with tie in connection points footings and many more to mention. Sometimes you can’t touch one item until you removed and supported it braced it or added extra members.

Below is a photo of where we were contracted to do the works.

Annerley start

DSC00959

 

DSC00967

 

DSC00968

As a cost saving measure I suggested to the clients to demolish as much as they could to pull down clean up etc. Once things were more visible regarding the structure we consulted with the engineer to work out a building solution and the most cost effective way to move forward on the project.

The Process

It was decided that parts of the besser block walls in the garage area had to be demolished as there was no structural steel bracing or core filling in certain sections. Not only that no external waterproofing had been done to a required wall and water and moisture was coming through the blocks.

We had to dig and remove soil as well. This was because we needed room to waterproof and re-fill in with 20mm drainage gravel wrapped in geo fabric and a 100mm socked aggi pipe below.

The other task we had was to dig footings by hand for the new post deck locations. We made up cages and put them into position. It made our job so much easier when we had to put 140 kg post into position on multi levelled ground by crane. You can bolt up straight away as well as level the posts with the bolts.

Crane posts

At the same time we also decided to do the block laying and core filling. Tip if you are doing any in ground work it is best to finish it off in one go. That way if it rains, weather will not delay your works.

Block laying

A two storey steel deck was to be fabricated wrapping itself along two sides of the house. This is all hot dipped gal so it needs to be pre fabricated and go together like a big Mecano set. New connections had to be made to be able to connect the pole plates. Once that was done the brick layers bricked around the penetration fixing points.

connection points

 

Pole plates were then bolted to the structure to also work as a brace when the steel rigging was in place. This makes the build and erection safer.

DSC02585

 

Once the house structural steel work was in place we placed all the load bearing beams in for the suspended concrete deck. We allowed a couple of months for adequate curing to reach its optumim strength normally no less then 28 days.

 

DSC02586

 

Once the Bondek was placed we then built the alfresco or pool house. With the trusses built and the roof on it was now ready for the deck pour.

2015-04-29 08.20.43

The clients also wanted the pool coping made by us so we did all the form works and did that pour before the slab pour. The reason we did that was because we had to have control joints between both and it was best to do the coping first. As it is all exposed polished concrete we only had one shot at it and as anyone in the building game knows with concrete is not forgiving. I have a good crew of concrete ors and I always take their advice if they have any to give.

2015-06-04 08.25.27

 

2015-05-19 13.43.03

2015-05-20 09.43.29

2015-06-04 08.22.55

2015-06-04 09.30.33 HDR

Vibration is critical very important for two reasons. First if makes the concrete flow to small crevasses corners and settles it well. The other reason all air pockets are minimised and so when boxing/ formwork is removed you are left with a good finished edge.

2015-06-04 08.38.17